New Jersey Administrative Code
Title 7 - ENVIRONMENTAL PROTECTION
Chapter 14A - NEW JERSEY POLLUTANT DISCHARGE ELIMINATION SYSTEM
Subchapter 22 - TREATMENT WORKS APPROVALS, SEWER BANS, SEWER BAN EXEMPTIONS
Section 7:14A-22.20 - Activities which do not require an exemption from the Department
Current through Register Vol. 56, No. 18, September 16, 2024
(a) Any project which has proceeded in accordance with a valid stage II and stage III treatment works approval from the Department for the construction and operation of treatment works will not require a sewer ban exemption from the Department provided that construction of the facilities is undertaken in accordance with the Department's approval.
(b) For projects which do not require a treatment works approval pursuant to 7:14A-22.4, a sewer ban exemption from the Department is not required provided that the owner/applicant of the project has obtained a building permit prior to the effective date of the sewer connection ban, and is otherwise lawfully entitled to initiate construction in conformance with previously issued valid approvals.
(c) Modifications, additions or deletions to the internal plumbing or piping of any lawfully, pre-existing building will not require a sewer ban exemption provided that:
(d) The replacement, rehabilitation or modification of existing conveyance and treatment facilities will not require a sewer ban exemption provided that the project does not involve any additional contributory flow, as determined by the Department.