(a) The seller must initially submit to the Executive Director a written request for approval of any proposed change in ownership. The request must contain a detailed description of the terms of sale or other ownership changes and a statement of the reasons for the proposed sale. The seller must also identify in detail and in a written report, the present physical, financial, management and tenant needs of the housing project. The Agency will review this report for completeness and accuracy, may require additional information or revisions to the report and may conduct its own review of the housing project's condition and operation.
(b) All essential parties within the seller's organization documents must approve the transfer or sale. An affidavit and opinion of the seller's legal counsel must be submitted to the Agency as proof of the legality of the transfer pursuant to the seller's Partnership Agreement or any other document and all applicable laws and regulations. An opinion of the buyer's legal counsel may also be requested by the Agency.
(c) In selecting the prospective buyer, the seller may solicit as many proposals as it deems necessary. Bidding is not required. The seller may negotiate among prospective buyers to obtain the best financial package/offer. Full and complete disclosure as to the nature and amount of the transaction must be made in writing to the Agency.
(d) As a condition of approving the transfer, the Agency will require that the housing project be restored to sound physical condition in accordance with the report submitted by the seller and the independent review by the Agency. Deferred maintenance must be corrected at the time of transfer unless otherwise approved by the Agency. Necessary repairs and capital improvements must be completed within a time frame acceptable to the Agency. A schedule for performing the work and a letter of credit or bond in the amount needed to complete the work must be provided to the Agency at closing.
(e) Cash contributions must be sufficient to fund both immediate and anticipated reserve needs. The mortgage and all fees and charges due the Agency must be current at the time of closing. All housing project reserve accounts must be funded to an acceptable level, as determined by the Agency, within 12 months from the date of transfer in accordance with the Agency's repair and replacement funding schedule.
(f) Contributions toward the purchase price from any sources other than cash proceeds must be identified.
(g) Upon assignment and assumption of the Agency's mortgage, modifications shall be made to the mortgage clearly specifying the Agency's right to enforce these regulations.