(a)
Each bidder's statement of qualifications shall contain, at a minimum, the
following:
1. An organizational chart of the
bidder and the key team members of the proposed design-build team;
2. A list of current construction projects,
and construction projects completed within the last five years, on which the
bidder and key team members of the proposed design-build team have worked that
are of similar size, scope, and complexity to the contracting unit's project,
regardless of method of project delivery;
3. A listing of all the contracting unit's
public works projects on which the design-builder and proposed design-build
team have performed work within the past five years;
4. For transportation projects, the minimum
classifications and aggregate rating limits to which the bidder and, as
applicable, key team members and other subcontractors have been assigned by the
New Jersey Department of Transportation pursuant to N.J.A.C. 16:44-3 and
16:44A-3, as applicable to the project. When a transportation project includes
the installation, replacement, or rehabilitation of associated water, sewer, or
stormwater infrastructure, the design-build team shall also possess
classifications and aggregate rating limits issued by the New Jersey Division
of Property Management and Construction in the New Jersey Department of the
Treasury (DPMC) that are relevant to such work;
5. For all projects other than transportation
projects, documentation that the bidder and, to the extent necessary for the
project, key team members and other subcontractors have a current DPMC
design-build classification and such other DPMC classifications and ratings
issued pursuant to N.J.A.C. 17:19-1, as may be necessary for the project . Key
team members and other subcontractors shall be required to possess only those
classifications and ratings issued by the DPMC that are relevant to the
project;
6. A listing of all public
works projects for which a contracting unit has made a determination of prior
negative experience with respect to the design-builder or members of its
proposed design-build team within the past five years pursuant to
N.J.S.A.
40A:11-4 or
18A:18A-4;
7. Training certification s of the bidder's
professional and field workforce, along with that of the members of the
proposed design-build team;
8.
Safety experience modification rating (EMR) of the bidder and construction
members of its proposed design-build team;
9. Measures taken by the bidder and members
of the proposed design-build team to promote workforce diversity with respect
to women and minorities;
10. If the
contract is subject to any set-aside goals established by the contracting unit
pursuant to P.L.
1985, c. 482 (N.J.S.A.
40A:11-41 et seq.), or
P.L.
1985, c. 490 (N.J.S.A.
18A:18A-51 et seq.), as applicable, a
statement as to whether the design-builder and/or any key team members are a
qualified minority business enterprise, a qualified women-owned business
enterprise, a qualified small business enterprise, or a qualified veteran-owned
business enterprise, as defined pursuant to the applicable law. Documentation
supporting such a designation shall accompany the statement;
11. If the design-build contract will be
subject to a project labor agreement pursuant to
P.L.
2002, c.
44(N.J.S.A. 52:38-1 et
seq.), a statement to that effect;
12. A copy of the bidder's Public Works
Contractor Registration certificate, along with a copy of the certificates of
the proposed members of the bidder's design-build team required to be
registered under the law;
13. A
certification that the bidder, along with the bidder's proposed design-build
team, including individually named key team members, is in compliance with, and
is not currently debarred from awards of State or local contracts for one or
more violations of, the New Jersey Prevailing Wage Act, Public Works Contractor
Registration Act, and the Construction Industry Independent Contractor Act;
and
14. A certification that the
bidder, along with the bidder's proposed design-build team including individual
key team members, is not debarred from awards of Federal contracts for public
work, as defined at
N.J.S.A.
52:32-44.1.
(b) The technical review committee shall
review and evaluate each bidder's statement of qualification and determine the
relative ability of each such bidder to perform the work under the design-build
contract. Before evaluating a bidder's statement of qualification, the
committee shall:
1. Verify with the Department
of Labor and Workforce Development that the bidder and any listed members of
the bidder's proposed design-build team, including individually named key team
members, that are required to have Public Works Contractor Registration
certificates, are current with their respective registrations;
2. Review the Department of Labor and
Workforce Development's Prevailing Wage Debarment List to confirm that the
bidder and any listed members of the bidder's proposed design-build team,
including individually named key team members, are not currently debarred;
and
3. Review the Federal
government's debarment database to confirm that the bidder and any listed
members of the bidder's proposed design-build team, including individually
named key team members, and affiliates thereof are not debarred, pursuant to
N.J.S.A.
52:32-44.1;
(c) The evaluation of the qualifications of
each bidder shall include, but need not be limited to, consideration of the
following factors:
1. The level of experience
of the bidder and the key team members of its proposed design-build team on
design-build projects and/or design-bid-build projects of similar size, scope,
and complexity;
2. Training
certification of the bidder's professional and field workforce, along with that
of the members of the proposed design-build team;
3. Safety experience modification rating
(EMR) of the bidder and construction members of its proposed design-build
team;
4. Measures taken by the
bidder and key team members to promote workforce diversity with respect to
women and minorities; and
5. Any
other pertinent information necessary to establish the qualifications of the
bidder and proposed design-build team to undertake the design-build
contract.
(d) The
process for evaluating the bidder's prior performance on the contracting unit's
prior designbuild projects, if any, by a technical review committee shall be
specified in the RFQ. Such process shall consist of:
1. A mathematical tabulation and averaging of
the scores of all prior performance evaluations within a specified time
period;
2. Consideration of
particularly favorable or unfavorable evaluations individually and with
reference to other evaluations;
3.
Consideration of multiple evaluations over the course of a given project, to
show consistency of performance, deterioration of performance, or efforts at
improvement and recovery; or
4. A
combination of the above methodologies.
(e) On the basis of the submitted statements
of qualification, the technical review committee shall qualify no fewer than
two, but no more than six, of the bidders to submit proposals. The contracting
unit shall provide written notification to all bidders submitting statements of
qualification of whether or not they have been being prequalified to receive
requests for proposal. All bidders shall have the right to review statements of
qualification submitted to the contracting unit.
(f) Key team members shall not be replaced
without approval of the technical review committee. The committee shall have a
reasonable basis for any denial.