Section 5:30-11.3 - General requirements for all change orders

Universal Citation: NJ Admin Code 5:30-11.3

Current through Register Vol. 56, No. 18, September 16, 2024

(a) No changes in quantities, work performed, services rendered, materials, supplies or equipment delivered or provided shall be authorized, permitted or accepted except by the procedures established herein. All change orders unless otherwise stated in this subchapter shall be subject to the following:

1. Each change order shall be in writing and shall be numbered consecutively (beginning with number one) and attached to the original purchase order or contract for each project.

2. Change orders which result in payment reduction below the originally contracted price may be made by locally established procedure, provided that any change orders increasing cost on the same contract shall include reference to such reductions.

3. Quantities of items or work shall not be changed in such a manner as to nullify the effect of the competitive determination of lowest responsible bidder which was made at the time of contract award, if at said time the changes could have been reasonably foreseen.

4. Responsibility required by these rules to be exercised specifically by the governing body, including authorization of change orders, shall not be delegated except for minor field (site) modifications pursuant to 5:30-11.4.

5. Change orders may be executed by the representative appointed by the governing body but the responsibility for the authorization of change orders shall not be delegated by the governing body except for minor field (site) modifications pursuant to N.J.A.C. 5:30-11.4.

6. Change orders shall be used to change the number of units or items originally advertised and contracted for, provided that:
i. Unit prices or a price methodology were sought in the original specifications and included in the contract;

ii. The original specification and the contract included a provision that the unit prices could be so used; and

iii. If (a)6i and ii above were not contained in the original specification, a change order shall not be issued.

7. Change orders shall not be used to substantially change the quality or character of the items or work to be provided, inasmuch as such would have been a determining factor in the original bidding.

8. Change orders shall not serve the purpose of escalation clauses and, therefore, shall not be utilized to effectuate upward price adjustments.

9. Total number of change orders executed for a particular contract shall not cause the originally awarded contract price to be exceeded by more than 20 percent unless otherwise authorized by these rules.

10. If proposed change orders do exceed the 20 percent limitation of (a)9 above, no work shall be performed or purchases made until the procedures of 5:30-11.9 have been completed. If the governing body determines issuance of the change order is not justifiable, a new contract shall be executed in accordance with the Local Public Contracts Law.

11. Before authorizing any change orders resulting in additional expenditures, the availability of funds shall be certified in writing by the chief financial officer or certifying finance officer, as appropriate.

12. The 20 percent limitation of (a)9 above shall not apply to emergency situations as defined within 40A:11-6.

13. Change order authorizations shall not be withheld until the completion of the entire project.

Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.