ENGINEERING SURVEY OUTLINE:

(NOTE: The engineering survey shall be in narrative form and include, but not be limited to description and condition of all applicable items in the outline below, in the order listed. The outline is intended as an aid to the inspecting architect or engineer and not as a questionnaire.)

Address

Block Number, Lot Number

Zoning

Year Built

Copy of last inspection report under the Hotel and Multiple Dwelling Law (55:13A-1 et seq.)

Violations outstanding--building, housing, air pollution, fire, other authorities

Alterations--date, number and brief description

Class of Construction (fireproof, non-fireproof, etc.)

Site:

Location

Size--dimensions, acreage

Streets--project owned or public

Paving--material

Curbing--material

Sidewalks--material

Drainage

Catch basins--type sewers

Street lighting

Drives--paving, curbing, drainage

Off street parking areas--paving, curbing, drainage

Utilities: give company or municipality furnishing service

Water supply

Sanitary sewers

Gas

Electric

Telephone

Sub-soil conditions including water conditions

Number of buildings and use

Structural System:

Steel or concrete frame

Other--describe

Type of foundations

Exterior of Building:

Walls (describe wall materials on all sides at all levels)

Insulation--"R" number

Window (types and materials) in all parts of building

Sills

Grilles

Stormsash

Screens

Hardware

Single or double glazing

Caulking

Parapets and copings--materials

Chimneys and caps: number and materials for each

Boilers

Incinerators

Fireplaces

Other

Balconies and Terraces:

Deck finish

Balustrade (type and material)

Copings

Railings

Soffit

Doors to balcony--type and material

Tenant entrances:

Marquees

Canopy

Exterior doors

Vestibule doors

Exterior stairs

Railings

Other

Service entrances:

Doors

Gates

Exterior stairs

Railings

Other

Roofs and Roof Structures:

Type roofs (for all areas)

Material (give number of plies if built up)

Insulation--"R" number

Surface finish

Age

Bond or guarantee (if any)

If old roof is re-covered, give date and description

Flashing materials

Drains

Gutters and leaders

Skylights

Bulkheads--wall materials

Stair

Elevator

Other

Water tank enclosure (if any)

Metal work at roof levels:

Exterior metal stairs

Ladders

Railings

Other

Fire Escapes:

Number

Type

Material

Yards and Courts:

Paving

Drainage

Railings

Stairs

Fencing or walls

Other

Interior Stairs:

Number of stairs of each type

Enclosure--construction and interior finishes

Stair construction

Treads and risers--materials

Railings

Elevators:

Number of passenger and service elevators

Manufacturer

Age

Type of operation and speed (ft. per minute):

Manual

Automatic (type controls)

Doors (sliding, swinging, manual, automatic)

Date and description of improvements

Location of machine rooms

Type of machine and input power

DC to motor

AC to motor

Description of cabs

Floor

Walls

Ceiling

Date of last inspection (e.g. government, maintenance contract, etc.)

Laundry Rooms:

Location and number of rooms

Washers--number

Dryers--number

Laundry trays--number

Room ventilation

Dryer ventilation

Operation (co-op owned, common element or concession)

Refuse Disposal:

Method of disposal

Number of incinerators or compaction units

Approval by authority having jurisdiction

Storage location

Pick-up schedule

Public or contract collection

Plumbing and Drainage:

Water supply

Source or company--approvals as required

Meters--individual or common charges

Piping--materials, age, condition, insulation

(Date and description of replacement or major improvements)

Describe system, pumps, storage

Fire protection system--standpipes, hoses, sprinklers, siamese connections

Water storage tanks

Number

Material

Location

Capacity--fire reserve

Water pressure

Sanitary sewage system

Piping--age and materials

Sewage pumps (if any)

Sewage disposal--public, private, treatment, drainfield, sewer

Storm Drainage System

Piping--age and materials

Pumps (if any)

Method of disposal

Heating:

Method

Number of boilers

Fuel

Manufacturer of boilers, age and date of installation

Manufacturer of burners, age and date of installation

Date of boiler inspection

Capacity of oil tank

Location of oil tank

Date and description of major changes or improvements to system

Type of controls

Description of radiators, piping, insulation, valves, pumps, etc.

Method of heating and distributing domestic hot water

Ventilation:

System--describe

(Include windowless areas, halls, garages, laundries, kitchens, baths)

Air Conditioning:

Type system-central system or individual units

Window unit ownership--tenant, common element or co-op

Water tower, air-cooled condensers--location

Gas Supply:

Type--bottled or main service

Meters--individual or common

Piping--material, condition

Pest Control:

Need and frequency of service

Electrical:

Date of installation

Improvements--date and complete description

Meters--common or individual

Service entrance equipment including:

Voltage and current ratings

Phases

Ratings of main fuses, distribution breakers or fuses to apartments

Adequacy of:

Service (average number circuits per apartment and capacities)

Lighting and fixtures

Convenience outlets; appliance outlets (average number per room including air-conditioner outlets)

Intercommunication system and door signal system

Switchboard

Television reception facilities:

Master antenna--apartment outlet distribution

Cable t.v.

Antenna by tenants

Security t.v.

Number cameras, monitors

Description and adequacy of lighting:

Entrance

Halls and stairs

Yard

Site

Garages and Parking Areas:

Location

Number of parking spaces and how allocated

Type of parking (attended?)

Ventilation--method

Fire protection

Drains

Recreation Facilities:

Swimming pool--approval by authorities

Replacement Cost:

A good faith estimate of the replacement cost of major structural components, such as but not limited to heating and air conditioning systems, plumbing system and roof.

Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.