Section 5:23-8.8 - Certificate of occupancy; certificate of completion

Universal Citation: NJ Admin Code 5:23-8.8

Current through Register Vol. 56, No. 18, September 16, 2024

(a) Certificate of occupancy requirements are as follows:

1. It shall be unlawful to re-occupy the portion of a building that was vacated during an asbestos hazard abatement project until a certificate of occupancy has been issued by the enforcing agency. The certificate of occupancy shall be issued upon receipt of a certificate of completion issued by the asbestos safety control monitor and verified by the enforcing agency that the building or a portion of a building is in conformance with all applicable requirements of the Uniform Construction Code and that any walls, floors, trim, doors, furniture or other items damaged during the work shall be repaired or refinished to match existing materials.

2. The application for a certificate of occupancy shall be in writing and submitted in such form as the Department may prescribe and shall be accompanied by the required fee as provided for in this subchapter.
i. The application shall include the following:
(1) The name and address of the owner;

(2) The address of the building or structure;

(3) Certificate of Completion submitted by the asbestos safety control monitor.

3. If all the information required is complete and in accordance with this subchapter, a certificate of occupancy shall be issued.

(b) Certificate of Completion requirements are as follows:

1. It shall be unlawful to apply for a certificate of occupancy until a certificate of completion has been issued by the asbestos safety control monitor.

2. Within five days of completion of an asbestos hazard abatement project the owner/agent shall file for a certificate of completion from the asbestos safety control monitor.

3. The application for a certificate of completion shall be in writing and submitted in such form as the department may prescribe.

4. A Certificate of Completion shall be issued only if:
i. All information is complete.

ii. Final inspection by the asbestos safety technician reveals no visible evidence of asbestos.

iii. All requirements of this subchapter have been met.

iv. An acceptable final air monitoring level has been attained pursuant to 5:23-8.21 and documentation of that air level has been submitted in writing.

Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.