Current through Register Vol. 56, No. 24, December 18, 2024
(a) The
requirements of this section are intended to prevent contamination and exposure
of building occupants to asbestos fibers.
(b) The building owner shall notify building
occupants in writing 20 business days prior to the commencement of an asbestos
abatement project. The building owner shall outline in writing any procedures
and/or precautions that are deemed necessary in order to protect the health,
safety and welfare of the occupants. This notification shall include, but not
be limited to: relocation plans, if any; entrances and exits that may
temporarily be blocked and alternate routes to be used; the name and telephone
number of the owner's representative for the occupant to call in case of an
emergency or to answer any questions with regard to the project. This
notification shall accompany the application for a construction permit for
asbestos abatement and shall be filed with the enforcing agency.
1. This notification shall be posted seven
days prior to the preparation of the work area, in visible locations, for the
benefit of the affected occupants of the work place, and in areas immediately
adjacent to the asbestos abatement project. It shall be the owner's
responsibility to ensure that these postings are maintained throughout the
project.
2. When circumstances
require immediate removal of asbestos-containing material, notification shall
be provided to the building occupants as soon as possible.
3. Nothing in this section shall be
interpreted as prohibiting the building owner from providing additional
notification.
4. The asbestos
safety control monitor firm shall notify the Department in writing 10 days
prior to the commencement of an abatement project in an occupied
building.
(c) A building
or structure or part thereof may be occupied during an asbestos abatement
project when all of the following conditions are met:
1. Isolation conditions include a requirement
that the work area be physically separated from occupied areas by separation
barriers of rigid construction consisting of nominal two inch by four inch
studs spaced 16 inches on center and covered with a minimum of one-half inch
plywood or comparable metal framing and 1/2 inch gypsum board covering. All
seams shall be caulked to render the barrier air tight before two layers of
polyethylene sheeting are applied on both sides. The polyethylene sheeting
shall overlap at the seams. All penetrations around conduits, pipes, ducts or
other openings between the work area and adjacent spaces shall be sealed, using
materials determined to be suitable in accordance with the applicable subcode.
In buildings required by the Uniform Construction Code to be of noncombustible
construction, all materials used to construct separation barriers shall meet
the Uniform Construction Code, building subcode requirements for that building
and all plastics used shall be flame resistant. A separate means of egress for
abatement personnel, materials and equipment shall be maintained. Adequate fire
evacuation routes shall exist for all building occupants at all times.
i. Whenever the building in which this work
area is located exceeds four stories in height and when stair, elevator or
similar shafts lie within or adjacent to the separation barriers or the work
area, then special seals shall be installed. Such seals shall be constructed in
the same manner as the separation barriers and shall create a space not less
than three inches in depth in front of the entire access area which space is
sealed on both sides and positively pressurized with HEPA filtered air so that
the pressure in the sealed space is .05 inches w.c. greater than that in the
work area or the shaft.
ii. All
HVAC systems located in the work area shall be shut down. If HVAC equipment is
located in the work area and must be operated to service other areas of the
building, then the HVAC equipment shall be isolated from the remainder of the
work area by an enclosure constructed in a manner similar to the separation
barriers and the space between the equipment and the seal shall be positively
pressurized with HEPA filtered air to at least .05 inches w.c. greater than the
work area.
iii. Where return air
ductwork which must be kept operating is located within the work area, then it
shall be isolated from the work area by an enclosure forming an annular space
around the duct which is positively pressurized with HEPA filtered air to at
least .02 inches w.c. greater than the work area. The enclosure shall be
constructed in a manner similar to that required for separation
barriers.
iv. All electrical
systems in the work area shall be shut down. Their use may be approved by the
asbestos safety control monitor if they are properly protected by ground fault
circuit interruptors, they are cleanable, and provided that such other
precautions as may be necessary are taken to ensure the safety of all who are
in the work area.
2.
Engineering controls shall be implemented as follows:
i. The asbestos safety technician shall
verify exhaust capacity through appropriate field measurement and record these
results in writing. The verification of exhaust flow rate via use of devices
for monitoring pressure drop across filters on air filtration devices shall not
be a substitute for appropriate field measurement. All exhaust from the work
area shall be directed to the exterior of the building. If exhaust to the
exterior of the building is not feasible, exhaust from the work area shall be
directed into a second set of in-line air filtration devices, which, then,
shall be permitted to be discharged into designated spaces approved by the
asbestos safety control monitor.
ii. The contractor shall install a sufficient
number of HEPA filter equipped air filtration units to cause a complete air
change or total air filtration within the work area at least once every 15
minutes. (Nothing in this subchapter shall be construed to limit the maximum
exhaust capacity from the work area or to prohibit additional air changes per
hour.) The exhaust capacity from the work area shall be sufficient to establish
a pressure differential between the work area and all adjacent spaces greater
than or equal to 0.05 inches w.c. (Nothing in this subchapter shall be
construed to limit the maximum pressure differential established between the
work area and occupied spaces.)
(1) Make up
air shall not be drawn through openings in the separation barriers in buildings
greater than four stories in height, unless those openings are equipped with
systems or devices which will not permit air flow except toward the work area
and the air filtration and exhaust units located in the work area.
3. Work area protection
shall be assured as follows:
i. Floors shall
be covered with two layers of polyethylene sheeting which shall overlap at the
seams and which shall be applied to the floor, individually sealed. The first
layer shall extend up the wall at least 12 inches. The second floor layer shall
be installed and extend up sidewalls at least 24 inches.
ii. Walls shall be covered with one layer of
polyethylene sheeting individually sealed to the wall. The layer shall hang
straight down overlapping the second layer of floor sheeting on the wall by at
least 18 inches.
iii. Sheeting
shall be sized to minimize the number of seams. No seams shall be located at
the joints between walls and floors. As a minimum, no seam shall stop within 12
inches of a corner and sheeting shall overlap at least 12 inches between seams
of adjacent layers.
iv. When a
strippable coating is used in place of polyethylene sheeting, it shall be used
in accordance with
N.J.A.C.
5:23-8.15(f)7 and the
product shall be applied during periods of minimal occupancy as determined by
the owner and included in the approved plan.
4. Monitoring shall be conducted as follows:
i. Air sampling shall be done as follows:
(1) At a minimum, one sample at the beginning
of each work shift, one every four hours thereafter, and one at the end of the
contractor's work day for every 10,000 square feet of occupied space adjacent
to the work area shall be collected and analyzed. Air samples shall be taken in
areas where the greatest potential for fiber migration exists. In addition to
the requirements noted above, air samples shall be taken at the entrance(s) to
the work area and any other interior spaces from which make-up air is drawn.
Additional samples shall be taken for all areas such as stairwells,
communicating shafts, elevators, plenums, ducts which pass through the work
area and which are in service, and unusual room and building configurations. If
air levels exceed the permitted fiber count, the applicable requirements of the
contingency plan in (c)5 below shall be followed.
(A) At least one air sample shall be
collected and analyzed during the work shift inside the work area. The results
of this test will not, however, trigger the requirements of the contingency
plan.
(2) A secure chain
of custody for air samples shall be established in writing as part of the
approved plan by the asbestos safety control monitor firm. The final
disposition of samples (whether they should be retained or disposed of after
analysis and if retained, who keeps them) shall be determined prior to the
commencement of asbestos abatement.
(3) The services of a testing laboratory, as
delineated in
N.J.A.C.
5:23-8.21(a)1 and 2, shall
include a microscope and laboratory technician at the project site or the
capacity to obtain results within four hours from start of sample. The
laboratory technician shall be listed in the Asbestos Analyst Registry of the
American Industrial Hygiene Association for PCM analysis or qualified by other
programs recognized by the Department as equivalent. If the laboratory
technician is on site, the owner shall provide a safe and clean space for the
analysis of samples separate and distinct from the work area. Air samples are
to be analyzed via NIOSH 7400 and verbal results made available for a
determination regarding continued occupancy. A written record of test results
shall be kept at the job site and included in the final report.
(4) Ten percent of all abatement samples
shall be re-analyzed within 24 hours at a laboratory for quality control
purposes.
(5) Daily occupancy shall
be allowed when the results of all the air samples are less than or equal to
0.010 fibers/cc by Phase Contrast Microscopy. If air levels exceed 0.010
fibers/cc, the contingency plan during abatement in (c)5 below shall be
followed.
(6) In the case of
reoccupancy and final clearance, all air samples used to determine reentry
shall be analyzed by an accredited laboratory.
ii. Pressure monitoring shall be carried out
as follows:
(1) Pressure differential shall
be monitored by digital manometers with continuous printout or other approved
low pressure monitoring devices. Sensor tubes used for monitoring shall be
placed so that the air filtration devices shall not cause false readings. The
asbestos safety technician shall zero and level the gauges each time a reading
is taken.
(2) One or more separate
pressure monitoring systems shall be installed by the asbestos safety control
monitor firm near the entrance(s) to the work area and between the work area
and any interior spaces from which make-up air is drawn.
(3) Written documentation of pressure
differential shall be provided by the asbestos safety technician either by
continuous printout devices. The asbestos safety technician and the contractor
supervisor will ensure, prior to the completion of the work shift, the
integrity of the containment site before workers depart.
(4) The pressure differential shall be
greater than or equal to 0.05 inches w.c. at the pre-commencement inspection
(at the time of approval immediately prior to the start of abatement work).
(A) In addition to providing a pressure
differential greater than or equal to 0.05 inches w.c. for the pre-commencement
inspection, a smoke test shall be conducted to demonstrate that the work area
has been isolated properly and that the pressure differentials have been
established to prevent fiber migration from the work area.
(5) Daily Occupancy shall be allowed when the
pressure differential is equal to or exceeds 0.05 inches w.c. If the air
pressure differential drops below 0.05 inches w.c., the contingency plan during
abatement in (c)5 below shall be followed.
5. Contingency plan during abatement shall be
implemented as described below. These are the minimum requirements which shall
be enforced by asbestos safety control monitors. These requirements shall not
limit the asbestos safety control monitors from instituting additional
requirements, if necessary, for the protection of the building occupants.
i. If the pressure differential drops below
0.05 inches w.c., the following procedures shall be implemented:
(1) The asbestos safety technician and the
contractor supervisor shall investigate and evaluate the engineering controls
to determine the source of the pressure loss.
(2) The contractor shall institute corrective
action such as: additional sealing, critical barrier maintenance and
construction, changing of exhaust unit filters, adjustment of make-up air,
operation of additional exhaust units or other necessary measures to
reestablish an acceptable pressure differential.
ii. If the pressure differential drops below
0.01 inches w.c., the following procedures shall be implemented:
(1) The contractor shall cease abatement
activity in the work area.
(2) The
asbestos safety control monitor shall notify the building owner to evacuate the
pressurized space(s). The pressurized space(s) shall include all space outside
the work area which is pressurized to maintain the required pressure
differential relative to the work area and is isolated from the rest of the
building in terms of air flow. The pressurized space may include the entire
building exclusive of the work area or any part of the building that is
pressurized to isolate it from the work area.
(3) The asbestos safety technician and the
contractor supervisor shall investigate and evaluate the engineering controls
and determine the source of the pressure loss.
(4) The contractor shall institute corrective
action such as: additional sealing, critical barrier maintenance and
construction, changing of exhaust unit filters, adjustment of make-up air,
operation of additional exhaust units or other necessary measures to
reestablish an acceptable pressure differential.
(5) Reoccupancy shall not be permitted in any
area unless a pressure differential of 0.05 inches w.c. or greater is
reestablished.
(6) If a pressure
differential of 0.05 inches w.c. or greater is not reestablished within 24
hours of the first reading below 0.01 inches w.c., then the building shall be
evacuated.
iii. If air
levels exceed 0.010 f/cc, the following procedures shall be implemented:
(1) The asbestos safety technician and the
contractor supervisor shall investigate and evaluate the engineering controls
to determine the source of the high air level.
(2) An additional/second PCM air sample shall
be taken at each place at which a high air level was obtained. The
additional/second PCM sample may be split, and if the result of the air sample
is less than or equal to 0.010 f/cc the contingency plan is terminated. If the
result of the air sample exceeds 0.010 f/cc, the contractor, in consultation
with the asbestos safety control monitor, shall choose the option of cleaning
and retesting by PCM analysis or analyzing the split sample by TEM analysis. If
the result of the TEM analysis exceeds 0.010 f/cc, then cleaning shall be
undertaken.
(3) The decision as to
the timing of the cleaning activity shall be made by the asbestos safety
control monitor firm in consultation with the building owner and the
contractor.
(4) Cleaning shall
include, but not be limited to, wet wiping and misting the air. Cleaning the
affected area shall be continued outside of containment and PCM sampling shall
also be continued until the result in the area is equal to or less than 0.010
f/cc by either PCM or TEM analysis.
(5) If laboratory analysis of air samples
does not yield a reading less than or equal to 0.010 f/cc within 24 hours of
receipt of the first test result above 0.010 f/cc, then the building shall be
evacuated.
(6) Reoccupancy shall
not be permitted in any area where PCM analysis reveals results greater than
0.010 f/cc, unless TEM results indicate asbestos fibers are equal to or less
than 0.010 f/cc. In the case of reoccupancy, all air samples used to make the
determination to allow reentry shall be analyzed by an accredited
laboratory.
iv. If a
power outage occurs during active abatement work, the building occupants shall
be evacuated until the air samples determine that the occupied spaces are safe,
and power has been restored. If a power outage occurs when the building is
unoccupied, occupancy will not be permitted until air samples determine that
the spaces to be occupied are safe and power has been restored.
6. Security shall be required as
follows:
i. In high risk areas, the owner
shall provide a 24 hour security guard to ensure protection against damage or
vandalism to separation barriers, engineering systems, monitoring devices, or
other equipment.
ii. The owner
shall provide continuous unlimited access for the asbestos safety technician in
all occupied spaces for installation, maintenance, and data collection from
monitoring systems.
iii. The
asbestos safety control monitor firm shall include provisions in the plan and
the asbestos safety technician shall ensure that filters are changed as
necessary and that pressure differential is maintained around the clock until
the project is completed.
7. Waste removal shall be accomplished as
follows:
i. The waste removal route of travel
is to be designated on the abatement plans and shall be separate and distinct
from the normal route of travel used by building occupants. Waste removal shall
occur during the time of least amount of building occupancy. If the route of
travel is to be used the following day by building occupants, air monitoring
must be performed, and if the results of air levels exceed 0.010 f/cc, then the
waste removal route is to be wet wiped using amended water, HEPA vacuumed and
retested until an acceptable air level is achieved prior to allowing occupancy
of the area.
ii. The waste removal
process shall be closely monitored visually and through air sampling by the
asbestos safety technician.
iii. No
dumpster shall remain on the premises overnight unless the dumpster is locked
and labeled to indicate that it contains asbestos-contaminated waste.
8. A written statement shall be
signed by the asbestos safety control monitor denoting that an asbestos
abatement will occur during building occupancy and verifying that the above
requirements will be maintained. This written statement shall accompany the
application for a construction permit for asbestos abatement and shall be filed
with the enforcing agency. This statement shall include the areas to be
occupied during the abatement and the number of occupants.