Current through Register Vol. 56, No. 18, September 16, 2024
(a) Tier one radon
hazard areas shall be identified in accordance with the county/municipal radon
listing established by the Department of Environmental Protection. The current
list of municipalities in tier one areas is set forth in Appendix 10-A of this
subcode.
(b) Group E buildings: The
construction techniques set forth in this subsection shall be the minimum radon
hazard protective features required to be incorporated into construction of
buildings in tier one areas, and may be incorporated elsewhere, in order to
minimize radon and radon progeny entry and facilitate any postconstruction
radon removal that may be required. Enumeration of these construction
techniques is not intended to preclude voluntary use of additional or more
extensive techniques. Full compliance with these construction techniques is not
required for additions; however, those construction techniques that are
feasible shall be incorporated.
1. A base
course in accordance with Section 1805.4.1 of the building subcode shall be
installed below slabs and foundations. There shall be a continuous base course
under each soil gas vapor barrier that is separated by foundation walls or
footings. Punctures, tears, and gaps around penetrations of the soil gas vapor
barrier shall be repaired or covered with an additional soil gas vapor barrier.
i. The soil gas vapor barrier shall be a
continuous 6-mil (0.15 mm) polyethylene or an approved equivalent.
ii. Approved alternative soil gas collection
areas, such as sealed crawlspaces, shall be permitted.
2. Foundation walls and floors in contact
with the soil shall be damp-proofed or waterproofed in accordance with Section
1805 of the building subcode.
3.
There shall be an unobstructed path for soil gas flow within the base course
and out through the vent in the roof.
4. Soil gases below the foundation shall be
collected by a perforated pipe with a diameter of not less than four inches and
not less than 10 feet in total length that is mechanically fastened to a "T"
pipe with two horizontal openings within the base course for radon collection
or an equivalent method.
i. The "T" pipe
fitting connection within the base course and the soil gas vent pipe that
extends to the roof shall be designed to prevent clogging of the radon
collection path.
ii. Alternately
the soil gas collection shall be by approved radon collection mats or an
equivalent approved method.
5. Openings in slabs, soil gas vapor
barriers, and joints, such as plumbing, ground water control systems, soil gas
vent pipes, piping, and structural supports, shall be sealed against air
leakage at the penetrations with a polyurethane caulk, expanding foam, or other
approved sealing method.
6. Gaps,
seams, and joints below grade in walls and footings that surround soil gas
collection areas shall be closed with cementitious materials, damp-proofing, or
other approved products.
7. Closure
shall be provided to prevent air migration between the base course that serves
soil gas collection and the foundation drain systems located outside of the
walls or footings that surround the soil gas collection areas.
8. Masonry unit walls below grade shall
provide a barrier between soil gas and interior spaces. Barriers shall include,
but not be limited to, closure of openings within the hollow masonry units,
full grouting, solid masonry units, or other approved method.
9. A sump cover that substantially closes off
the soil gas entry routes shall be provided for all sump
installations.
10. Sumps intended
for ground water control shall have gasketed lids or be otherwise sealed and
shall not be connected to the soil gas exhaust system.
11. Vent pipes shall connect to a single vent
that terminates at least 12 inches above the roof. If the design requires
multiple individual vent pipes, they shall terminate separately at least 12
inches above the roof. Alternatively, vent pipe termination from the soil gas
permeable layer shall extend to at least 30 feet above grade. In addition, vent
pipes shall meet the following:
i. The vent
pipe shall terminate no less than four feet vertically above or 10 feet
horizontally away from operable windows, doors, or skylights.
ii. The vent pipe shall be sloped to avoid
collecting condensate or rainwater.
iii. The vent pipe size shall not be reduced
at any location as it goes from gas collection to the roof.
iv. Exposed and visible interior vent pipes
shall be identified with not less than one label reading "Radon Reduction
System" on each floor .
v. The
minimum vent pipe diameter and maximum area vented per vent pipe shall be as
specified in Table 11 below.
vi.
Multiple sub-slab areas that are segregated and combined into a single vent
pipe shall be subject to minimum vent pipe diameter and maximum area vented per
vent pipe specifications in Table 11 below.
TABLE 11
Maximum Vented Foundation Area
Maximum Area Vented |
Minimum Pipe Diameter |
2,500 ft<2> |
3 inch |
4,000 ft<2> |
4 inch |
Unlimited |
6 inch |
12. In buildings that have interior footings
or other barriers that separate the soil gas permeable layer, each area shall
be fitted with an individual vent pipe.
13. Electrical junction boxes shall be
installed within six feet of the provided area, such as an accessible attic
space, where a future in-line vent pipe fan and system failure alarms may be
installed.*
(c) Group R
buildings: The construction techniques set forth in this subsection shall be
the minimum radon hazard protective features required to be incorporated into
construction of buildings in tier one areas, and may be incorporated elsewhere,
in order to minimize radon and radon progeny entry and facilitate any
post-construction radon removal that may be required. Enumeration of these
construction techniques is not intended to preclude voluntary use of additional
or more extensive techniques. Full compliance with these construction
techniques is not required for additions; however, those construction
techniques that are feasible shall be incorporated.
1. A continuous vapor barrier not less than
six-mil (.006 inch; .152 mm) polyvinyl chloride or polyethylene with any seams
overlapped not less than 12 inches (305 mm), or other approved materials, shall
be installed under the slab in basement and slab-on-grade construction and on
the soil in crawl space construction.
2. Floors of basements and slab on grade
construction shall be placed over a base course, not less than four inches (102
mm) in thickness, consisting of gravel or crushed stone containing not more
than 10 percent of material that passes through a No. 4 sieve.
3. Basement slabs with interior foundation
pipe drains installed shall have a solid three-inch minimum diameter vent pipe
section installed in conjunction with this drainage system and be connected to
an independent vent stack pipe terminating at an approved location on the
exterior of the building.
4.
Basement slabs which do not have an interior foundation pipe drain, and slab on
grade construction (excluding non-habitable spaces such as garages), shall be
provided with one three-inch minimum solid vent pipe section with a "T" pipe
fitting for every 1,500 square feet, or portion thereof, of slab area, this
vent pipe section to be installed into the sub-slab aggregate. The horizontal
openings of the "T" pipe fitting shall be placed in the sub-slab aggregate. The
vertical portion of the "T" pipe fitting shall be connected to an independent
vent stack pipe terminating at an approved location on the exterior of the
building. Where more than one vent pipe section is provided, interconnection of
these sections into a single independent vent stack is permitted.
5. Basement slabs with French drains or
channel drains shall not be allowed unless interior foundation pipe drains as
described in this section are installed.
6. Joints in foundation walls and floors,
including, without limitation, control joints between slab sections poured
separately, and between foundation wall and floor (except for French drains or
channel drains), as well as penetrations of the foundation walls and floor
including, but not limited to, utility penetrations, shall be substantially
sealed by utilizing a non-cracking polyurethane or similar caulk, or
equivalent, in order to close off the soil gas entry routes. Any openings or
penetrations of the floor over the crawl space shall be substantially sealed in
order to close off the soil gas entry routes.
7. Untrapped floor drains shall be provided
with removable stoppers which substantially close off the soil gas entry
routes.
8. A sump cover which
substantially closes off the soil gas entry routes shall be provided for all
sump installations. If foundation pipe drains terminate at a sump installation
and provisions are made for venting from the sump installation, the three-inch
diameter solid vent pipe section requirement of (b)3 above need not be
provided.
9. Any ductwork that is
routed through a crawl space or beneath a slab shall be properly taped or
sealed.
10. Sealant materials that
substantially close off the soil gas entry routes shall be installed on any
doors or other openings between basements and adjoining crawl spaces that are
vented to the exterior.
11. The
tops of foundation walls, including, without limitation, interior ledges, that
are constructed of hollow masonry units shall be capped or the voids shall be
completely filled.
12. The
independent vent stack pipe provided in accordance with (b)3, 4 or 8 above
shall be an adequately supported, gas tight, three-inch minimum diameter solid
pipe, through any enclosed portions of the building. The pipe shall be routed
in a manner that makes it accessible for the installation of a future in-line
vent pipe fan in a non-conditioned (not heated or cooled) space, including,
without limitation, an attic space, but excluding a basement or crawl space,
and installed in a configuration, and supported in a manner, that will ensure
that rain water or condensate accumulation within the pipes will drain downward
into the ground beneath the slab or vapor barrier. The vent stack pipe shall
meet the following termination requirements:
i. Vent pipes shall terminate at least 12
inches above the roof, measured from the highest point where the vent
intersects the roof. When a vent pipe extension terminates on an occupiable
roof the vent pipe shall extend at least seven feet above the roof surface.
Exception: Buildings more than three stories in height shall be allowed to
extend vent pipe terminals through a wall provided that the termination is at
least 20 feet above grade and is effectively screened.
ii. No vent terminal shall be located
directly beneath any door, window, or other ventilating opening of the building
or of an adjacent building nor shall any such vent terminal be within 10 feet
horizontally of such an opening unless it is at least two feet above the top of
such opening.
iii. No vent terminal
shall be closer than 10 feet horizontally from any lot line. Where this 10 foot
horizontal distance is not possible due to lot width, the vent terminal shall
be placed as remote from the lot line as practicable.
13. Radon vent pipes shall be identifiable
and clearly labeled at intervals of not more than 25 feet in concealed
locations, not more than 50 feet in exposed locations and not less than once in
any room or space.
14. Electrical
junction boxes shall be installed near the provided area, such as an accessible
attic space, where a future in-line vent pipe fan and system failure alarms may
be installed.
15. In combination
basement/crawl space or slab-on-grade/crawl space buildings a three-inch
minimum solid vent pipe shall be provided between the areas and interconnected
into the independent vent stack to permit use of a single in-line vent pipe fan
if activation of the system is desired.
16. In order to reduce stack effect, air
passages that penetrate the conditioned envelope of the building, such as attic
access openings, or other openings installed in top-floor ceilings, shall be
closed, gasketed or otherwise sealed with materials approved for such
applications.