Section 16:44-10.2 - Percent withheld pending completion of contract

Universal Citation: NJ Admin Code 16:44-10.2

Current through Register Vol. 56, No. 18, September 16, 2024

(a) Two percent of the amount due on partial payments of the total adjusted contract price will be deducted and retained by the Department pending substantial completion. Upon substantial completion of the contract, as defined at N.J.A.C. 16:45, one percent will be withheld.

(b) At any time during the performance of the work, if work is not progressing as defined by the current edition of the Department's Standard Specifications for Road and Bridge Construction, the Commissioner has discretion to increase the withholding to four percent of the payment due.

Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.