New Jersey Administrative Code
Title 16 - TRANSPORTATION
Chapter 41F - VEGETATION CANOPY MANAGEMENT
Subchapter 6 - VCM PLANS
Section 16:41F-6.3 - Plan review and approval
Current through Register Vol. 56, No. 24, December 18, 2024
(a) The Bureau of Landscape Architecture and Environmental Solutions (BLAES) review of a proposed VCM Plan shall not begin until all materials listed in N.J.A.C. 16:41F-6.1(b) have been received.
(b) The Operations Permit Office review of the highway occupancy permit application shall not begin until all permit application information and the permit application fee have been received.
(c) The BLAES and the Operations Permit Office will concurrently review the proposed VCM Plan and the highway occupancy permit application and, within 45 days of application submission, advise the applicant if the submission is deemed complete.
(d) Within 45 days of the submission being deemed complete, the applicant shall be advised if the proposed VCM Plan is approved, if it must be modified, or if it is rejected and the reasons for the rejection.
(e) The highway occupancy permit that will govern the VCM Plan shall not be issued until the proposed VCM Plan is approved by the BLAES.