(a) When an applicant proposes to undertake multiple activities that are associated with different types of permits, the fee associated with the highest cost permit shall be applicable.

(b) Anyone under contract to the Department and working on Department rights-of-way or on property under the jurisdiction of the Department at the written request of the Department shall not be assessed an application or permit fee for any required permit.

(c) Fees for applications, permits, and extensions are set forth below and are non-refundable. Fees shall be in the form of a check or money order made payable to the Department. The Department shall not accept cash. The applicant shall submit the application fee with the application. The applicant shall not submit the permit fee until the applicant returns the signed proposed permit to the Operations Permit Office. The Department shall not execute a proposed permit until the applicant has submitted the proper fee for the permit and the applicable entity identified at 16:41-6.1 has signed the proposed permit.

Type Number Unit Application Permit Extension
Utility 0 to 20 Square Feet $525.00 $200.00 $200.00
Openings (SF)
20 to 200 SF $790.00 $265.00 $265.00
Greater than 200 SF $1,185.00 $395.00 $395.00
Poles 1 to 10 Unit $330.00 $100.00 $100.00
Greater than 10 Unit $625.00 $200.00 $200.00
Curb, Sidewalk, or Handicapped Ramp 0 to 200 Linear Feet (LF) $395.00 $130.00 $130.00
Greater than 200 LF $790.00 $265.00 $265.00
Drainage 1 to 5 Unit $230.00 $65.00 $65.00
Facilities
Greater than 5 Unit $525.00 $200.00 $200.00
0 to 200 SF $230.00 $65.00 $65.00
Greater than 200 SF $525.00 $200.00 $200.00
Landscaping, Tree Trimming, Vegetation Control, or Unclassified Unit $395.00 $130.00 $130.00
Landscaping
Bridge Attachments 0 to 100 LF $395.00 $130.00 $130.00
Greater Than 100 LF $790.00 $265.00 $265.00
Pedestrian Overpass or Underpass 1 Unit $790.00 $265.00 $265.00
Grading Unit $330.00 $100.00 $100.00
Guiderail 0 to 200 LF $395.00 $130.00 $130.00
Greater than 200 LF $790.00 $265.00 $265.00
Test Holes or Borings 1 to 5 Unit $230.00 $65.00 $65.00
Greater than 5 Unit $460.00 $165.00 $165.00
Monitoring Wells 1 to 5 Unit $230.00 $65.00 $65.00
Greater than 5 Unit $460.00 $165.00 $165.00
Crosswalks 1 to 4 Unit $230.00 $65.00 $65.00
Greater than 4 Unit $460.00 $165.00 $165.00
Bus Unit $395.00 $130.00 $130.00
Shelters or Benches
Banners, Decorations, or Temporary Announcements or Guide Signs 1 to 5 Unit $165.00 $35.00 $35.00
Greater than 5 Unit $230.00 $65.00 $65.00
Parades or Gatherings Unit $165.00 $35.00 $35.00
Temporary Use $460.00 $165.00 $165.00
Detours off State Highways or Vice Versa Unit $395.00 $130.00 $130.00
Lane or Shoulder Closings on State Highways Unit $230.00 $65.00 $65.00
Automatic Traffic Counting Procedure Unit $65.00 $35.00 $35.00
Wireless Communications Annual Unit $790.00 $265.00 $265.00
Site Survey
Railroad Grade Crossings Unit $525.00 $200.00 $200.00
Miscellaneous Unit $395.00 $130.00 $130.00
VCM Site Investigation Unit $ 395.00 $ 130.00 $ 130.00
VCM Plan Unit $ 2,000 $ 1,000 NA

Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.