(a) Where the Department determines that the public utility facility installation is feasible, the Department will establish, within the right-of-way of limited access highways, a corridor, generally not closer than 30 feet to the edge of roadway, but contiguous to each side of the roadway's control of access line, for the installation of underground utility facilities. Should such an exception allow a public utility facility to be placed within 15 feet of the edge of pavement, the facility shall be installed within a casing or with a protective layer in accordance with 16:25-9.4(c)4 and 5.
(b) Consideration will be given by the Department for prudent utilization of the corridor to provide for multiple occupancy; however, the Department will not reserve space within said corridor for any particular facility or utility.
(c) At interchange areas, the installation corridor shall continue along the control of access boundary outside of the outermost roadway or ramp.