New Jersey Administrative Code
Title 14 - PUBLIC UTILITIES
Chapter 9 - WATER AND WASTEWATER
Subchapter 11 - WASTEWATER SYSTEM IMPROVEMENT CHARGE
Section 14:9-11.6 - WSIC-eligible plant investments during a base rate case
Current through Register Vol. 56, No. 6, March 18, 2024
(a) In the event that WSIC-eligible plant additions are placed in service during the test year of a wastewater utility's base rate case, if not recovered as part of a routine WSIC filing, those plant additions shall be considered as part of the base rate case proceeding, and included in the routine test-year plant additions, consistent with existing Board rules.
(b) Notwithstanding the other provisions of this subchapter, a wastewater utility may continue to make WSIC-eligible investments and collect a WSIC charge during a pending rate case filed in accordance with existing Board rules.
(c) WSIC rates shall be rolled into base rates during a wastewater utility's subsequent base rate case and the WSIC rate shall be reset to zero.