New Jersey Administrative Code
Title 14 - PUBLIC UTILITIES
Chapter 8 - RENEWABLE ENERGY AND ENERGY EFFICIENCY
Subchapter 5 - INTERCONNECTION OF CLASS I RENEWABLE ENERGY SYSTEMS
Section 14:8-5.5 - Level 2 interconnection review
Current through Register Vol. 56, No. 18, September 16, 2024
(a) Each EDC shall adopt a level 2 interconnection review procedure. The EDC shall use the level 2 interconnection review procedure for an application to interconnect a customer-generator facility that meets both of the following criteria:
(b) For a customer-generator facility described at (a) above, the EDC shall approve interconnection under the level 2 interconnection review procedure if all of the applicable requirements at (c) through (l) below are met. An EDC shall not impose additional requirements not specifically authorized under this section.
(c) The aggregate generation capacity on the line section to which the customer-generator facility will interconnect, including the capacity of the customer-generator facility, shall not cause any distribution protective equipment (including, but not limited to, substation breakers, fuse cutouts and line reclosers) or customer equipment on the electric distribution system, to exceed 90 percent of the short circuit interrupting capability of the equipment. In addition, a customer-generator facility shall not be connected to a circuit that already exceeds 90 percent of the short circuit interrupting capability, prior to interconnection of the facility.
(d) If there are posted transient stability limits to generating units located in the general electrical vicinity of the proposed point of common coupling (for example, within three or four transmission voltage level busses), the aggregate generation capacity (including the customer-generator facility) connected to the distribution low voltage side of the substation transformer feeding the line section containing the point of common coupling shall not exceed 10 MW.
(e) The aggregate generation capacity connected to the line section, including the customer-generator facility, shall not contribute more than 10 percent to the line section's maximum fault current at the point on the high voltage (primary) level nearest the proposed point of common coupling.
(f) If a customer-generator facility is to be connected to a radial line section, the aggregate generation capacity connected to the electric distribution system by non-EDC sources, including the customer-generator facility, shall not exceed 10 percent (or 15 percent for solar electric generation) of the total circuit annual peak load. For the purposes of this subsection, annual peak load shall be based on measurements taken over the 12 months prior to the submittal of the application, measured at the substation nearest to the customer-generator facility.
(g) If a customer-generator facility is to be connected to three-phase, three wire primary EDC distribution lines, a three-phase or single-phase generator shall be connected phase-to-phase.
(h) If a customer-generator facility is to be connected to three-phase, four wire primary EDC distribution lines, a three-phase or single phase generator shall be connected line-to-neutral and shall be effectively grounded.
(i) If a customer-generator facility is to be connected to a single-phase shared secondary, the aggregate generation capacity on the shared secondary, including the customer-generator facility, shall not exceed 20 kilovolt-amps (kVA).
(j) If a customer-generator facility is single-phase and is to be connected to a transformer center tap neutral of a 240 volt service, the addition of the customer-generator facility shall not create an imbalance between the two sides of the 240 volt service, which is greater than 20 percent of the nameplate rating of the service transformer.
(k) A customer-generator facility's point of common coupling shall not be on a transmission line.
(l) If a customer-generator facility's proposed point of common coupling is on a spot or area network, the interconnection shall meet all of the following requirements that apply, in addition to the requirements in (c) through (k) above:
(m) An applicant shall submit an Interconnection Application/Agreement Form for level 2 interconnection review. The standard form is available from the EDC, and includes a Part 1 (Terms and Conditions) and a Part 2 (Certificate of Completion).
(n) Within three business days after receiving an application for level 2 interconnection review, the EDC shall provide written or e-mail notice to the applicant that it received the application and whether the application is complete. If the application is incomplete, the written notice shall include a list of all of the information needed to complete the application.
(o) Within 15 business days after the EDC notifies the applicant that the application is complete under (n) above, the EDC shall notify the applicant by e-mail or in writing of one of the determinations at (o)1 through 4 below, as applicable. During the 15 business days provided under this subsection, the EDC may, at its own expense, conduct any studies or tests it deems necessary to evaluate the proposed interconnection and arrive at one of the following determinations:
(p) Once a customer-generator receives Part 1 of the application with the EDC signature in accordance with (o)1, 2 or 3 above, and has installed and interconnected the customer-generator facility to the EDC's distribution system, the customer-generator shall obtain approval of the facility from the appropriate construction official, as defined at 5:23-1.4.
(q) At least 10 business days prior to starting operation of the customer-generator facility (unless the EDC does not require 10 days notice), the customer-generator shall:
(r) The EDC may require an EDC inspection of a customer-generator facility prior to operation, and may require and arrange for witness of commissioning tests as set forth in IEEE standard 1547 (published July 2003) in accordance with the following:
(s) If an application for level 2 interconnection review fails to meet the requirements as described at (o)3 or 4 above, or is denied because it does not meet one or more of the requirements in this section, the applicant may resubmit the application under the level 3 interconnection review procedure.