New Jersey Administrative Code
Title 14 - PUBLIC UTILITIES
Chapter 8 - RENEWABLE ENERGY AND ENERGY EFFICIENCY
Subchapter 5 - INTERCONNECTION OF CLASS I RENEWABLE ENERGY SYSTEMS
Section 14:8-5.4 - Level 1 interconnection review
Current through Register Vol. 56, No. 18, September 16, 2024
(a) Each EDC shall adopt a level 1 interconnection review procedure. The EDC shall use the level 1 review procedure only for an application to interconnect a customer-generator facility that meets all of the following criteria:
(b) For a customer-generator facility described at (a) above, the EDC shall approve interconnection under the level 1 interconnection review procedure if all of the applicable requirements at (c) through (g) below are met. An EDC shall not impose additional requirements not specifically authorized under this section.
(c) The aggregate generation capacity on the line section to which the customer-generator facility will interconnect, including the capacity of the customer-generator facility, shall not contribute more than 10 percent to the distribution circuit's maximum fault current at the point on the high voltage (primary) level that is nearest the proposed point of common coupling.
(d) A customer-generator facility's point of common coupling shall not be on a transmission line, a spot network, or an area network.
(e) If a customer-generator facility is to be connected to a radial line section, the aggregate generation capacity connected to the circuit, including that of the customer-generator facility, shall not exceed 10 percent (15 percent for solar electric generation) of the circuit's total annual peak load, as most recently measured at the substation.
(f) If a customer-generator facility is to be connected to a single-phase shared secondary, the aggregate generation capacity connected to the shared secondary, including the customer-generator facility, shall not exceed 20 kilovolt-amps (kVA).
(g) If a single-phase customer-generator facility is to be connected to a transformer center tap neutral of a 240 volt service, the addition of the customer-generator facility shall not create an imbalance between the two sides of the 240 volt service of more than 20 percent of nameplate rating of the service transformer.
(h) An applicant shall submit an Interconnection Application/Agreement Form for level 1 interconnection review. The standard form is available from the EDC, and includes a Part 1 (Terms and Conditions) and a Part 2 (Certificate of Completion).
(i) Within three business days after receiving an application for level 1 interconnection review, the EDC shall provide written or e-mail notice to the applicant that it received the application and whether the application is complete. If the application is incomplete, the written notice shall include a list of all of the information needed to complete the application.
(j) Within 10 business days after the EDC notifies the applicant that the application is complete under (i) above, the EDC shall notify the applicant that:
(k) If the EDC notifies the customer-generator under (j)1 above that the facility will be approved, the EDC shall, within three business days after sending the notice under (j)1 above, do both of the following:
(l) Once an applicant receives Part 1 of the application with the EDC signature in accordance with (k) above, and has installed and interconnected the customer-generator facility, the applicant shall obtain approval of the facility by the appropriate construction official, as defined at 5:23-4.1.
(m) The customer-generator shall submit documentation of the construction official's approval to the EDC, along with a copy of Part 2 of the application, signed by the customer-generator.
(n) If inspection of the customer-generator facility was waived under (k)1 above, the EDC shall, within five business days after receiving the submittal required under (m) above, notify the customer-generator of authorization to energize the facility. The notice to the customer-generator shall be provided in the format required under 14:8-5.2(i).
(o) If inspection of the customer-generator facility was not waived under (k)1 above, the following process shall apply:
(p) If an application for level 1 interconnection review is denied because it does not meet one or more of the applicable requirements in this section, an applicant may resubmit the application under the level 2 or level 3 interconnection review procedure, as appropriate.