New Jersey Administrative Code
Title 14 - PUBLIC UTILITIES
Chapter 8 - RENEWABLE ENERGY AND ENERGY EFFICIENCY
Subchapter 4 - NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS
Section 14:8-4.5 - Net metering reporting requirements for EDCs
Current through Register Vol. 56, No. 6, March 18, 2024
(a) Each EDC with one or more customer-generators connected to its distribution system shall submit two net metering reports per year, one covering January 1 through June 30 and one covering July 1 through December 31. The EDC shall submit the reports by August 1 and February 1, respectively.
(b) The EDC shall submit the reports required by this section electronically, in PDF format, to oce@bpu.state.nj.us. In addition, the EDC may, at its discretion, submit a paper copy of the reports by hand delivery or regular mail to the Secretary, Board of Public Utilities, 44 South Clinton Avenue, 9th Floor, PO Box 350, Trenton, New Jersey 08625-0350. The EDC may, at its discretion, submit the net metering report together with the interconnection report required under 14:8-5.9.
(c) Each report required in (a) above shall include the following information regarding customer-generator energy input and output during the reporting period:
(d) The report required in (a) above shall include the following information regarding credits and payments to customer-generators during the reporting period:
(e) For purposes of the reporting required under this section, any estimates shall be made using Board-approved protocols unless no such protocol is available, in which case the estimates shall be accompanied by detailed calculations demonstrating how the estimates were made.