New Jersey Administrative Code
Title 12 - LABOR AND WORKFORCE DEVELOPMENT
Chapter 190 - EXPLOSIVES
Subchapter 7 - USE OF EXPLOSIVES
Section 12:190-7.26 - Ground vibration

Universal Citation: NJ Admin Code 12:190-7.26

Current through Register Vol. 56, No. 18, September 16, 2024

(a) This section shall apply to ground vibrations on a construction closest to the nearest loaded blast hole to be detonated that are neither owned nor leased by the person conducting or contracting for the blasting operation.

(b) In planning any blast, precautions shall be taken to protect construction from damage.

(c) The limits for ground vibration when blasting shall be in accordance with Table 7.26(e) or (f) below. In no case shall the peak particle velocity at a construction exceed two inches per second except when permitted by N.J.A.C. 12:190-1.6.

(d) If the ground vibrations are not within the blasting criteria of (e) below due to either blast design or geological conditions, the Commissioner may require a modified control method for the blast site.

(e) This subsection shall apply to ground vibration limits for blasting operations.

1. The blasting shall be conducted so that the low frequency ground vibration does not exceed the limits of Figure 7.26(e).

Data in image

(f) This subsection shall apply to ground vibration limits for blasting operations utilizing a modified scaled distance established by petition.

1. At any site where blasting is of continuing nature with the blast design unchanged and geological conditions unchanging, the commissioner may be petitioned to set a modified scaled distance equation which would be less restrictive than (d), (e) or (f) above.

2. The petition shall include:
i. A written statement of the reasons for the request,

ii. A map showing residences within a radius of 3,000 feet of the blast site,

iii. A proposed method of establishing a modified scaled distance,

iv. An outline of the test procedures including monitoring of at least three blasts with approved instrumentation,

v. A map showing the exact placement of one instrument at the nearest building, the placement of one instrument at a distance of 2,000 feet from the blast, and the placement of a third instrument at some distance between the first two instruments,

vi. A proposed schedule for the test runs which shall be observed by the commissioner.

3. The instrumentation data shall be interpreted by a competent person. The modified scaled distance equation shall be based on the criteria established in (f) above. The modified scaled distance equation shall be prepared by a competent person and submitted to the commissioner for approval.

4. Upon approval by the Commissioner, the modified scaled distance equation may be used at the specific blast site in place of (e) above provided:
i. The conditions under which the testing was performed do not change,

ii. The procedure established is verified every six months,

iii. The modified scaled distance equation is not willfully disregarded.

(g) This subsection shall apply to instrumentation used in monitoring ground vibration limits.

(h) Instrumentation used in this section shall comply with the following:

1. All instruments used shall be operated by a competent person, and the recordings shall be interpreted by a competent person.

2. All instruments and instrumentation systems shall be considered approved only if the instrument meets the following criteria:
i. The instrument shall be calibrated in accordance with the manufacturer's recommendations but not less than once a year by a competent person;

ii. The instrument shall be capable of measuring and recording particle velocity displacement, or acceleration in three mutual perpendicular directions;

iii. The instrument shall have a seismic range from .005 to 10 inches per second (254 mm/s); and

iv. The instrument shall have a frequency response range from 2 to 300 hertz.

3. All instruments transducers shall be firmly coupled to the ground or be used in accordance with the manufacturer's recommendations.

4. The instrument shall be placed between a construction closest to the nearest blast hole to be detonated that is neither owned nor leased by the person conducting or contracting for the blasting operations. The instrument shall be set up as close to the construction as possible to comply with (h)3 above.Chapter Notes

Disclaimer: These regulations may not be the most recent version. New Jersey may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.