New Hampshire Code of Administrative Rules
Tra - Commissioner, Department of Transportation
Chapter Tra 500 - CONSTRUCTION AID AND RELOCATION SERVICES
Part Tra 502 - STATE HIGHWAY AID
Section Tra 502.12 - Contract Award and Administration
Universal Citation: NH Admin Rules Tra 502.12
Current through Register No. 40, October 3, 2024
(a) Department-managed projects shall be awarded to the lowest responsible bidder in a competitive bidding process conducted in accordance with RSA 228:4 and RSA 228:4-a. A department-managed project shall be administered by the department.
(b) A municipally-managed project shall be performed by a construction provider, under the following conditions:
(1) The construction provider was selected as
the lowest responsible bidder in a competitive bidding process;
(2) The municipality has submitted a
tabulation of the bids received in the competitive bidding process to the
department; and
(3) The department
has concurred in the contract award after considering the following, including,
but not limited to:
a. The reasonableness of
the unit prices in the bids; and
b.
If the construction provider is not prequalified in accordance with Tra 401,
the experience of the construction provider in the type of work anticipated in
the project.
(c) During construction, the work shall be inspected by the department as necessary to ensure conformity with the approved plans and specifications.
#8924, eff 6-27-07
Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.