(a) Once permanently installed on an approved foundation, a modular building or building component shall not be relocated within this state without prior written authorization from the department.
(b) Any modular building or building component being relocated shall meet all current state codes prior to issuance of a final certificate of occupancy.
(c) A manufacturer, builder/dealer or property owner shall complete and submit a written request for relocation with the department on form DSFM 121 "Modular Relocation Form", revised 10/2010.
(d) A written request for relocation pursuant to (c) above shall include the following, as applicable:
(e) If the request for relocation is approved, the department shall notify the requestor, in writing, within 10 business days, of its approval, with any compliance change noted.
(f) Upon notification by the responsible party, the department or the third party agency shall conduct a final certification of the modular building or building component and affix new state labels, in coordination with the authority having jurisdiction.
(g) The manufacturer, builder/dealer, or property owner shall submit a report to the department, within 5 business days of the date on which a relocated modular building or building component has been shipped into this state or relocated within this state, in accordance with the requirements of Saf-C 3309.09(c).
#5439, eff 7-24-92; ss by #6234, eff 4-27-96; ss by #6885, eff 11-18-98; ss by #8741, INTERIM, eff 11-18-06, EXPIRED: 5-17-07
New. #9752, eff 7-9-10