New Hampshire Code of Administrative Rules
Saf - Department of Safety
Subtitle Saf-C - Commissioner, Department of Safety
Chapter Saf-C 3300 - RULES FOR MODULAR BUILDINGS AND BUILDING COMPONENTS
Part Saf-C 3308 - APPROVAL OF MODULAR BUILDING AND BUILDING COMPONENT MANUFACTURERS
Section Saf-C 3308.02 - Renewal of Manufacturer
Current through Register No. 40, October 3, 2024
On an annual basis, no later than 45 days prior to the expiration of manufacturer approval pursuant to Saf-C 3308.01(d), the manufacturer shall submit the following to the department:
(a) A completed application, pursuant to Saf-C 3308.01, clearly reflecting any changes, amendments, or revisions to its building system or quality assurance program; and
(b) A renewal fee of $1000.00 to the department, pursuant to RSA 205-C:6.
#5439, eff 7-24-92; ss by #6810, INTERIM, eff 7-25-98, EXPIRES: 11-22-98; ss by #6885, eff 11-18-98;ss by #8741, INTERIM, eff 11-18-06, EXPIRED: 5-17-07
New. #9752, eff 7-9-10