(a) No building design shall be considered approved pursuant to Puc 1800 and RSA 155-D without the issuance of an approval number by the commission, except as provided in (b) and (c) below.

(b) A building design that a local authority having jurisdiction has approved in writing pursuant to RSA 155-D:4, II shall be deemed approved pursuant to (a) above.

(c) Pursuant to RSA 155-D:5, II, a building design shall be deemed approved for which:

(1) Plans have been certified as complying with the energy code by an architect or engineer pursuant to RSA 155-D:4,VI; or

(2) Plans have been deemed to be approved due to failure of the commission to act on a completed application within 15 working days of submittal pursuant to RSA 155-D:4, V.

#4702, eff 11-16-89; ss by #6152, INTERIM, eff 12-26-95, EXPIRED 4-24-96

New. #6333, eff 9-17-96; ss by #6879, eff 2-1-99, EXPIRED: 2-1-07

New. #8811, INTERIM, eff 2-2-07, EXPIRED: 8-1-07

New. #8958, eff 7-31-07

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.