(a) All new passenger tramways shall be subject to an inspection and a running test in accordance with ANSI B77.1-2017 standards effective 2017 and available as noted in Appendix B. The test shall be witnessed by an authorized representative or designee of the board.

(b) An authorized representative of the board pursuant to (a) above shall include:

(1) Engineers as designated by the board;

(2) Members of the tramway board; and

(3) The state of New Hampshire's chief of tramway safety or state tramway inspector.

(c) In the event of a modification to an existing passenger tramway, the testing requirements of the qualified engineer shall be completed. The board shall require testing of one or more components beyond that required by the qualified engineer if the board determines that the modification adversely affects the safety of the lift.

(d) The board shall be given 10 days advance notice that the tramway shall be ready for testing.

#2297, eff 2-7-83; ss by #2704, eff 5-9-84, EXPIRED 5-9-90 (formerly Saf-S 1005.05)

New. #4862, eff 7-10-90; amd by #6020, eff 4-14-95; ss by #6284, eff 7-10-96; ss by #7800, eff 12-11-02; amd by #9354-B, eff 1-3-09; EXPIRED: 12-11-10, except for para (a); ss by #10072, eff 1-11-12; amd by #10382, eff 7-23-13

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.