(a) Each applicant for a marine aquaculture license under RSA 211:62-e shall make application in writing to the executive director.
(b) The applicant shall complete and submit an application containing the following:
(c) Upon receipt of the application the executive director shall determine the completeness of the application and notify the applicant in writing within 30 days as to its completeness or describe fully any deficiency found.
(d) The department shall conduct a site assessment or evaluation for any area that has not had a site assessment completed within the previous 2 years. The department staff shall conduct the site assessment for purposes of verifying or updating data and information included in the application. Site assessments shall be conducted between May and October.
(e) The site assessment shall include but not limited to:
(f) After the complete application has been received and the department's site evaluation is complete, the executive director shall set a hearing date and notify the applicant of the date, time and location of the hearing.
(g) Upon being notified that the hearing date has been scheduled, the applicant shall:
(h) The notice to land owners required in Fis 807.07(g)(1) shall include:
(i) The executive director shall provide public notice in the newspaper of the scheduled hearing at least 21 days prior to the hearing. Any interested person may submit written comments on the proposed project to the executive director up to 14 days after the public hearing on the proposed aquaculture project.
(j) The executive director shall review all of the information to determine that the proposed aquaculture operation would not pose any unacceptable risk as specified in Fis 807.02(g), does not conflict with or negatively impact any recreational, commercial or other use currently being conducted in the area in and around the proposed project area, or does not adversely impact the value or use of private property in and around the projected area before issuing a license.
(See Revision Note at chapter heading for Fis 800) #5507, eff 11-20-92; ss by #6028, eff 4-27-95 (See Revision Note at part heading for Fis 807); ss by #6889, eff 11-21-98, EXPIRED: 11-21-06
New. #8767, INTERIM, eff 11-22-06, EXPIRED: 5-21-07
New. #8893, eff 6-5-07