The project-specific information required by Env-Wt 310.01(c)(1) or Env-Wt 311.03(b)(11), as applicable, for a dredge project shall be as follows:
(a) A description of the material and area to be dredged, including:
(b) The erosion and sediment control measures proposed to be used;
(c) The methods proposed to dewater the dredged material;
(d) The location at which dewatering will occur;
(e) The equipment proposed to perform the dredging;
(f) The proposed disposal site;
(g) Identification of all known potential sources of soil or water contamination;
(h) If potential sources are documented in (g), above, the method of sampling for contaminants and a plan to manage contaminated materials;
(i) A description of how dredged material will be contained during the dredging process; and
(j) An explanation of the timing of the project and how such timing helps minimize impacts on aquatic resources.