(a) A utility project shall be a minimum impact project if:
(1) The project meets all applicable Utility
BMPs, available as noted in Appendix B, and will have temporary impacts
associated with inspection, maintenance, repair, replacement, or removal of
existing utility facilities within existing rights-of-way;
(2) The project does not include establishing
new access roads, installing permanent stream or wetland crossings,
constructing new utility corridors or rights-of-way, or establishing new
utility assets within existing corridors or rights-of-way;
(3) The project does not include any
permanent fill in navigable waters;
(4) Impacts to any PRA other than prime
wetlands and duly-established 100-foot buffers are authorized by following the
recommendations provided by NHB, NHF&G, and the department;
(5) Timber mats are:
a. Not used in a tidal marsh; and
b. Used in an area other than a tidal marsh
only if they are:
1. Necessary to conduct
activities;
2. Removed as soon as
work is completed; and
3. In place
no longer than one growing season;
(6) The project does not cause a permanent
conversion of more than 3,000 SF in total of forested wetlands to emergent or
scrub-shrub wetlands with or without temporary fill; and
(7) For private residential utility projects
involving the installation of residential utility lines and associated
temporary impacts to bring services to a single building lot:
a. The total jurisdictional impact will not
exceed 3,000 SF;
b. Impact width at
any wetland crossing will not exceed 20 feet;
c. Stream crossing channels will not exceed 8
feet wide measured bank to bank; and
d. Only swamps or wet meadows that have no
standing water for 10 months of the year will be
crossed.
(b) A utility project shall be a minor impact project if the project:
(1) Includes the installation of one or more
new permanent crossing(s) of a perennial stream;
(2) Establishes a new access road, new
utility corridor or right-of-way, or new utility assets;
(3) Exceeds the Utility BMPs, available as
noted in Appendix B, or any of the minimum impact criteria in (a),
above;
(4) Includes permanent
conversion of forested wetlands to emergent or scrub-shrub wetlands with or
without temporary fill;
(5) For
private residential utility projects, exceeds minimum impact criteria but does
not exceed Env-Wt 400 project classification criteria; or
(6) Impacts greater than 3,000 SF but less
than 10, 000 SF or meets the requirements for minor impact classification
specified in Env-Wt 407.
(c) A utility project shall be a major impact project if:
(1) It does not meet the criteria
for a minimum or minor impact project;
(2) It exceeds the minor impact criteria or
meets the major impact criteria specified in Env-Wt 407; or
(3) It meets the criteria in (a) above, but:
a. Is in a PRA and has impacts that cannot be
addressed through recommendations by NHB, NHF&G, or the department, as
applicable; or
b. Requires
mitigation under state or federal law.
Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.