New Hampshire Code of Administrative Rules
Env - Department of Environmental Services
Subtitle Env-Wt - Wetlands Programs
Chapter Env-Wt 500 - PROJECT-SPECIFIC REQUIREMENTS
Part Env-Wt 520 - FORESTRY
Section Env-Wt 520.04 - Design and Construction Requirements
Current through Register No. 13, March 27, 2025
In addition to the design and construction requirements specified in Env-Wt 300, the following requirements shall apply to forestry activity projects:
(a) Impacts to surface waters and wetlands from logging activities shall be planned, designed, constructed, and stabilized in accordance with the University of New Hampshire Cooperative Extension's "New Hampshire Best Management Practices for Erosion Control on Timber Harvesting Operations," dated 2016 (Forestry BMPs), available as noted in Appendix B;
(b) All skid trails, truck roads, and log landings shall be:
(c) Crossings shall be removed when logging is completed in the area serviced by the crossing, except that corduroy crossings at location where there is no defined stream channel may be left in place.