Section Env-Wt 515.06 - Dug-In Basins and Boathouse, and Structures Regulated Under RSA 482-A:26 Construction or Modification Project Classification
Current through Register No. 13, March 27, 2025
(a) The construction or modification of a boathouse over an existing dug-in basin shall be a minimum impact project only if all of the following criteria are met:
(b) The modification of a boathouse over public submerged lands shall be a minimum impact project only if all of the following criteria are met:
(c) The construction or modification of a boathouse over an existing dug-in basin shall be a minor impact project if all of the criteria of (a), above, are met with either of the following exceptions:
(d) The modification of a boathouse over public submerged lands shall be a minor impact project if all of the criteria of (b), above, are met and less than 20 CY of material will be dredged.
(e) The construction or modification of a dug-in basin or boathouse that does not meet any of the classification criteria of (a) through (d), above, shall be a major project.