(a) The construction or modification of a boathouse over an existing dug-in basin shall be a minimum impact project only if all of the following criteria are met:

(1) The construction or modification is in accordance with Env-Wt 515.05;

(2) The boathouse and any associated docking structures are existing legal structures;

(3) No portion of the existing boathouse was made suitable for use as a dwelling contrary to RSA 482-A:26 prior to or subsequent to the effective date of the original prohibition, May 28, 1969;

(4) No additional boat slips will be provided as a result of the project; and

(5) Dredging will be limited to areas within the dug-in basin.

(b) The modification of a boathouse over public submerged lands shall be a minimum impact project only if all of the following criteria are met:

(1) There is no increase in the exterior dimensions of the boathouse;

(2) The boathouse and any associated docking structures are existing legal structures;

(3) No portion of the existing boathouse was made suitable for use as a dwelling contrary to RSA 482-A:26 prior to or subsequent to the effective date of the original prohibition, May 28, 1969;

(4) No additional boat slips will be created as a result of the project; and

(5) The boathouse modification does not include dredging.

(c) The construction or modification of a boathouse over an existing dug-in basin shall be a minor impact project if all of the criteria of (a), above, are met with either of the following exceptions:

(1) Additional boat slips will be provided as a result of the project but the total number of existing and proposed slips on the property will not exceed 4; or

(2) Less than 20 CY of material will be dredged from areas outside the dug-in basin.

(d) The modification of a boathouse over public submerged lands shall be a minor impact project if all of the criteria of (b), above, are met and less than 20 CY of material will be dredged.

(e) The construction or modification of a dug-in basin or boathouse that does not meet any of the classification criteria of (a) through (d), above, shall be a major project.

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.