Any concrete pad installed to anchor a seasonal pier shall:

(a) Be not more than 7 feet wide as measured along the shoreline;

(b) Not be in prime wetlands or a duly-established 100-foot buffer;

(c) Designed such that any adjacent bank stabilization, such as gravel or rip-rap, will not cause the total impact of the pad to exceed 10 LF along the bank;

(d) For a concrete pad on a pond or lake, be constructed landward of the normal high water line; and

(e) For a concrete pad on a watercourse, installed completely landward of the ordinary high water line.

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.