(a) Replenishment of sand on an existing beach shall be a minimum impact project only if all of the following criteria are met:

(1) The beach is an existing legal structure as defined in Env-Wt 102;

(2) No sand is placed below the normal high water line or limits of flowage rights, as applicable;

(3) No work is done in a wetland, watercourse, or PRA, except as provided in Env-Wt 407;

(4) No more than 10 CY of sand is used; and

(5) The beach is not replenished more frequently than once in any 6-year period.

(b) Replenishment of a beach shall be a minor impact project if the project meets the criteria in (a)(1)-(3), above, and either:

(1) The beach is replenished more frequently than once in a 6-year period; or

(2) More than 10 CY of sand but not more than 20 CY of sand will be used.

(c) Replenishment of an existing legal beach shall be a major impact project if the project does not meet the criteria specified in (a) or (b), above.

(d) A beach that is not an existing legal structure shall not be replenished unless an after-the-fact permit is obtained for construction of the beach, which shall be classified as provided in Env-Wt 511.06.

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.