The following conditions shall apply to all work done pursuant to an EXP:
(a) No other work shall be done on the subject property pursuant to another EXP, PBN, or an SPN for a period of 12 months from the date the EXP was issued unless the property owner submits information, including a plan, to demonstrate that:
(1) The proposed work is wholly unrelated to
and separate from the work already done under the EXP, PBN, or SPN;
and
(2) The proposed work and the
work already done under the EXP, PBN, or SPN do not, when combined, constitute
a project for which a standard permit is required;
(b) The work shall comply with all applicable conditions specified in Env-Wt 307; and
(c) Any work shall be timed and carried out to protect documented occurrences of cold water or threatened or endangered fisheries.
Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.