(a) Subject to (b)-(f), below, this chapter shall apply as of the 2019 effective date of the chapter to any person who undertakes or proposes to undertake any dredge, fill, or construction activities, or any combination thereof, in a jurisdictional area.
(b) The approval criteria in this chapter shall apply to:
(c) NH DOT projects that qualify for a statutory permit by notification (SPN) or the registration process established in Env-Wt 309.03 and Env-Wt 309.04 but have not been initiated prior to the 2019 effective date of this chapter shall be undertaken pursuant to the requirements of this chapter.
(d) NH DOT projects for which an application has been filed prior to the 2019 effective date of this chapter shall be subject to the design, approval, and construction criteria in effect on the date of filing, provided the application is complete within 6 months of the 2019 effective date of this chapter, regardless of when the completeness determination is made.
(e) If NH DOT believes that one or more projects in the planning stages for which an application has not been filed as of the 2019 effective date of this chapter should be subject to the design, approval, and construction criteria in effect prior to the 2019 effective date of this chapter, NH DOT shall submit a list in writing to the department of all such projects, that includes for each project:
(f) If NH DOT submits a list pursuant to (e), above, the department shall consult with NH DOT to reach a mutual agreement regarding the design features or other aspects of each project that are not practicable to redesign or otherwise change to meet the requirements of the 2019 rules and so will be subject to the rules in effect prior to the 2019 effective date of this chapter.
(g) For each project submitted by NH DOT, the agreement reached pursuant to (f), above, shall be memorialized in writing signed by authorized officials of the department and NH DOT.
(h) NH DOT shall submit a copy of the signed agreement required by (g), above, with the relevant application so that the agreement becomes part of the public file.