Section Env-Wq 1506.01 - Erosion Control Methods: Temporary and Permanent Mulching

Universal Citation: NH Admin Rules Env-Wq 1506.01

Current through Register No. 13, March 27, 2025

Mulching shall comply with the following:

(a) Hay and straw mulches shall be anchored with mulch netting or tackifier so that they are not blown away by wind or washed away by flowing water;

(b) Mulch materials shall be selected based upon soils, slope, flow conditions, and time of year;

(c) Hay or straw mulch shall be applied at a rate of 1.5 to 2 tons per acre, equivalent to 70 to 90 pounds per 1,000 square feet;

(d) Wood chips or ground bark shall be applied at 2 to 6 inches deep at a rate of 10 to 20 tons per acre, equivalent to 460 to 920 pounds per 1,000 square feet;

(e) Jute and fibrous mats and wood excelsior shall be installed according to the applicable manufacturer's instructions; and

(f) Erosion control mix shall:

(1) Meet the criteria of Env-Wq 1506.05(b); and

(2) Be placed at a thickness of 2 inches or more.

(See Revision Note #1 at chapter heading for Env-Wq 1500) #9343, eff 1-1-09

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.