(a) If precast masonry units are used for dry wells, the portion of the dry well above the inlet pipe shall be laid with mortared joints or otherwise strengthened.
(b) Hard-burned brick, heavy-weight concrete block, structural clay tile, and fieldstone shall be acceptable if properly laid to provide necessary structural strength.
(c) If cement blocks are used, the blocks shall be laid such that the holes run vertically.
(See Revision Note at chapter heading for Env-Wq 1000) #9086, eff 2-9-08
Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.