New Hampshire Code of Administrative Rules
Env - Department of Environmental Services
Subtitle Env-Wq - Water Quality and Quantity Programs
Chapter Env-Wq 1000 - SUBDIVISIONS; INDIVIDUAL SEWAGE DISPOSAL SYSTEMS
Part Env-Wq 1016 - CONSTRUCTION REQUIREMENTS FOR ALL EDA
Section Env-Wq 1016.08 - Storm Runoff
Universal Citation: NH Admin Rules Env-Wq 1016.08
Current through Register No. 13, March 27, 2025
Where sloping ground is used for construction of the EDA, a small temporary dike or surface water diversion ditch shall be constructed above the EDA to prevent the EDA from being washed out by rain. The dike shall be maintained or the ditch kept free of obstruction until the EDA becomes stabilized with vegetation, at which time the dike or ditch shall be filled in unless the setback distance in Env-Wq 1008.04, table 1008-2 are met.
(See Revision Note at chapter heading for Env-Wq 1000) #9086, eff 2-9-08
Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.