(a) Before backfilling the EDA, the stone shall be covered with a durable permeable layer that will allow ventilation, such as a 2 inch layer of hay or filter fabric. An impervious covering such as tar paper or plastic shall not be used, as this interferes with ventilation.

(b) Backfill material shall be clean, permeable fill.

(c) After backfilling, the top of the EDA shall be overfilled with 4 to 6 inches of loam suitable for seeding.

(d) No more than 18 inches total of backfill and loam shall be used to cover the EDA unless the effluent conduits are vented.

(e) Hydraulic backfilling or machine tamping of the backfill or loam, or both, shall be prohibited.

(See Revision Note at chapter heading for Env-Wq 1000) #9086, eff 2-9-08; amd by #9904-A, eff 4-16-11

Disclaimer: These regulations may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.