Current through Register No. 40, October 3, 2024
(a) Each year the committee shall review the cumulative nuclear decommissioning fund and each funding assurance in place pursuant to an order of the committee as provided in RSA 162-F:22, II.
(b) For each annual review, the owner shall file:
(c) No less than every 4 years, the committee shall review the projected cost of decommissioning the nuclear generating electric facility in addition to the annual review that is conducted each year.
(d) For each such review required in (c) above, the owner shall file a detailed study of the process and cost of decommissioning the nuclear electric generating facility including:
#4235, eff 2-20-87, EXPIRED: 2-20-93
New. #5700, INTERIM, eff 9-17-93, EXPIRED: 1-15-94
New. #5824, eff 8-30-94, EXPIRED: 8-30-00
New. #7366, INTERIM, eff 9-18-00, EXPIRED: 3-17-01
New. #9144-A, eff 4-24-08
New. #9144-B, eff 4-24-08