Nevada Administrative Code
Chapter 704B - Providers of New Electric Resources
TRANSACTIONS WITH ELIGIBLE CUSTOMERS
Section 704B.370 - Duty to file and serve certain agreements; limited review and use of certain underlying contracts; confidentiality; terms, conditions and compliance items; petition to reopen consideration of application; limitations on actions of Commission after approval of application
Current through December 31, 2024
1. Not later than 30 days before the eligible customer begins purchasing energy, capacity or ancillary services from the provider, the eligible customer shall file with the Commission the following agreements:
The detailed plan may include provisions for standby service, load shedding, recourse to reliably available market resources and any other measures or combination of measures reasonably designed to avoid involuntary load curtailments by the electric utility.
2. Each agreement filed with the Commission pursuant to subsection 1 must be served on each party of record.
3. Upon receipt of the agreements filed with the Commission pursuant to subsection 1, the Regulatory Operations Staff shall:
4. In addition to the terms, conditions and compliance items required by subsections 1 and 3, the Commission may condition its order approving an application with any other terms, conditions and compliance items it deems necessary to ensure that the proposed transaction is not contrary to the public interest.
5. The Commission will provide in each order approving an application that the eligible customer must comply with all terms, conditions and compliance items imposed pursuant to this section, if any, not later than 120 calendar days after the date on which the Commission issues the order.
6. A party of record may petition the Commission to reopen consideration of an application. A party of record must file such a petition not later than 15 calendar days after the date on which the Commission determines that the eligible customer has complied with all terms, conditions and compliance items imposed pursuant to this section.
7. Except upon a petition to reopen consideration of an application that is filed by a party of record pursuant to this section and except as otherwise provided in this section, or as may be needed to address any objections raised pursuant to NAC 704B.405, the Commission will not, after it issues an order approving an application:
Added to NAC by Pub. Utilities Comm'n by R125-01, eff. 12-17-2001; A by R018-04, 11-17-2005; A by R195-22A, eff. 9/16/2024
NRS 704B.200