Nevada Administrative Code
Chapter 704 - Regulation of Public Utilities Generally
Section 704.Sec. 13.1 - NEW

Universal Citation: NV Admin Code 704.Sec. 13.1

Current through September 16, 2024

The affiliated utilities may seek and obtain a waiver or deferral of a biennial energy storage target that falls within the 3-year period covered by the action plan. The request for a waiver or deferral must include, without limitation:

1. An explanation of why the procured cumulative amount of energy storage did not meet the biennial energy storage target, along with data and analysis supporting the assertions in this explanation.

2. A demonstration that an effort was made to solicit or develop the resources needed to meet the biennial energy storage target under consideration, with an explanation of why energy storage was not solicited or not selected if other resources were selected. The explanation may include, without limitation, the cost and benefits for energy storage, where benefits include all reductions in resource costs as well as cost savings associated with other services or alternatives that would have otherwise been procured.

Added to NAC by Pub. Utilities Comm'n by R106-19A, eff. 5/21/2020

NRS 703.025, 704.210, 704.796

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.