Nevada Administrative Code
Chapter 704 - Regulation of Public Utilities Generally
RIGHTS AND OBLIGATIONS OF CUSTOMERS OF CERTAIN ELECTRIC AND GAS UTILITIES
Section 704.344 - Adjustment of bill when meter inaccurate
Current through December 12, 2024
1. If a meter is tested pursuant to NAC 704.343 and is found to be inaccurate by more than 2 percent, the bill for service of any customer affected must be adjusted as provided in this section.
2. Except as otherwise provided in subsection 3, if the meter has:
3. If the utility establishes that the meter has been tampered with or used without its authorization, the adjustment must be calculated for a period not to exceed the most recent 6 months of usage or the date on which the tampering or unauthorized use began, whichever is greater.
4. A customer who, because of an adjustment to his or her bill, owes the utility money for service may pay that amount over a 3-month period.
5. The utility shall credit the account of a customer who was overcharged because of an inaccurate meter not later than 30 days after the overcharge is determined.
Added to NAC by Pub. Service Comm'n, eff. 1-5-89
NRS 703.025, 704.210