Nevada Administrative Code
Chapter 704 - Regulation of Public Utilities Generally
GENERAL PROVISIONS
Section 704.Sec. 11.2 - NEW

Universal Citation: NV Admin Code 704.Sec. 11.2

Current through February 27, 2024

1. On or before December 1, 2020, and every 3 years thereafter, an electric utility shall submit an expanded solar access program plan to the Commission for approval.

2. An electric utility may file an amendment to an expanded solar access program plan that has been approved by the Commission provided that another expanded solar access program plan submitted by the utility is not pending before the Commission.

3. Two or more utilities that are affiliated through common ownership may jointly file an expanded solar access program plan or amendment pursuant to this section.

4. Utility scale solar resources which are included in an expanded solar access program plan must be approved by the Commission in an order issued pursuant to NRS 704.751.

5. On or before March 1 of each calendar year following the calendar year in which the Commission approved the initial expanded solar access program plan of an electric utility, the electric utility shall file an informational report with the Commission which details:

(a) For the immediately preceding calendar year:
(1) The number of applications for the program received by the electric utility;

(2) The number of individuals who voluntarily left the program; and

(3) The number of participants remaining in the program at the end of the calendar year.

(b) The status of any community-based solar resources including, without limitation, the construction, maintenance and operation of such solar resources.

(c) The production of energy by community-based solar resources and utility scale solar resources which are included in the program.

(d) The amount of energy subscribed and whether the reserve capacity is adequate.

(e) Information regarding the expanded solar access program rate, including, without limitation, revenues received and costs incurred by the utility.

(f) Any workforce statistics related to the program that are available to the electric utility.

(g) The number and types of calls to the customer service department of the utility relating to the program.

(h) The number of individuals who did not return recertification documentation.

Added to NAC by Pub. Service Comm'n by R136-20A, eff. 12/22/2021

NRS 703.025, 704.210, 704.7865

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.