1. An amendment to an action plan submitted by a utility pursuant to NAC 704.9503 must contain:

(a) A section that identifies the items for which the utility is requesting specific approval;

(b) A section that specifies any changes in assumptions or data that have occurred since the utility's last resource plan was filed;

(c) As applicable, information required in paragraphs (d) and (e) of subsection 1 of NAC 704.9489, and subsections 3 and 4 of NAC 704.9489;

(d) As applicable, data and information required pursuant to NAC 704.922 to 704.948, inclusive, necessary to facilitate an evaluation of the items specified pursuant to paragraph (a) for which the utility is requesting specific approval;

(e) A current peak demand forecast;

(f) A table indicating the current loads and resources; and

(g) If the utility seeks an amendment related to a renewable energy contract or energy efficiency contract, information about the imputed debt mitigation.

2. For amendments submitted pursuant to paragraphs (a) and (f) of subsection 1 of NAC 704.9503, a utility shall file with the Commission the information required pursuant to paragraph (d) of subsection 1 of this section.

Added to NAC by Pub. Utilities Comm'n by R004-04, eff. 5-25-2004; A by R167-05, 2-23-2006

NRS 703.025, 704.210, 704.741

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.