Section 704.9457 - Acceptance or modification of emissions reduction and capacity replacement plan
Current through September 16, 2024
1. After a hearing, the Commission may issue an order accepting or modifying an emissions reduction and capacity replacement plan of an electric utility that primarily serves densely populated counties if the emissions reduction and capacity replacement plan or any modifications to the plan provide for:
2. In considering whether to accept or modify the emissions reduction and capacity replacement plan of an electric utility that primarily serves densely populated counties, the Commission will consider the factors set forth in subsection 8 of NRS 704.746 and the analyses related to those factors which is provided by the utility pursuant to paragraph (b) of subsection 7 of NAC 704.9453.
3. If the Commission issues an order modifying the emissions reduction and capacity replacement plan of an electric utility that primarily serves densely populated counties, the utility may accept the modifications made by the Commission or withdraw the emissions reduction and capacity replacement plan. If the utility withdraws its emissions reduction and capacity replacement plan pursuant to this subsection:
Added to NAC by Pub. Utilities Comm'n by R131-13, eff. 3-28-2014
NRS 704.7322, 704.741