Section 704.9378 - Supply plan: Time-line graphs for proposed resources for supply

Universal Citation: NV Admin Code 704.9378

Current through September 16, 2024

The supply plan must contain time-line graphs for the utility's proposed resources for supply that include major activities, milestones and points of decision. The following subjects must be included in the time-line graphs for each proposed resource:

1. Preparation of any required environmental impact statements;

2. Applications for significant permits;

3. Commitments of significant expenditures;

4. Periods for construction; and

5. The commercial operation date.

Added to NAC by Pub. Service Comm'n, eff. 2-18-88; A by Pub. Utilities Comm'n by R004-04, 5-25-2004

NRS 703.025, 704.210, 704.741

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.