Nevada Administrative Code
Chapter 704 - Regulation of Public Utilities Generally
ELECTRIC SERVICE
Resource Planning
Section 704.9208 - Dates for certain utilities to file resource plans

Universal Citation: NV Admin Code 704.9208

Current through September 16, 2024

1. The resource plans required to be submitted by Nevada Power Company pursuant to NRS 704.741 must be filed on July 1, 1988, and every 3 years thereafter.

2. The resource plans required to be submitted by Sierra Pacific Power Company pursuant to NRS 704.741 must be filed on July 1, 1989, and every 3 years thereafter.

Added to NAC by Pub. Service Comm'n, eff. 2-18-88; A by Pub. Utilities Comm'n by R004-04, 5-25-2004

NRS 703.025, 704.210, 704.741

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.