1. Each utility shall file annually with the Commission, in the format for a tariff, the:
2. The short-term avoided costs of each utility must be filed with the Commission within 60 days after the Commission issues an order accepting the utility's resource plan.
3. The short-term avoided costs for each utility must be the utility's most current projections for short-term capacity and energy costs.
4. As used in this section, "resource plan" has the meaning ascribed to it in NAC 704.9156.
Pub. Service Comm'n, Gen. Order 32 § 4.0, eff. 8-21-81-NAC A 2-18-88; 3-17-89; 3-27-92; A by Pub. Utilities Comm'n by R004-04, 5-25-2004
NRS 703.025, 704.210