Section 703.427 - Expiration and renewal of permit
Current through December 31, 2024
1. Any construction permit issued pursuant to NAC 703.415 to 703.427, inclusive, expires 5 years after the date of final action by the Commission unless during that period the applicant has commenced to construct the utility facility and has diligently pursued that construction. In computing the 5-year period, the time the construction of the utility facility is delayed or made impractical because of legal action against the applicant will be excluded.
2. The applicant may apply for renewal of a construction permit at any time before its expiration. The Commission will renew the permit upon a showing of good cause.
Added to NAC by Pub. Service Comm'n, eff. 3-19-87; A by Pub. Utilities Comm'n by R188-03, 7-16-2004; R076-07, 10-31-2007