Nevada Administrative Code
Chapter 703 - Public Utilities Commission of Nevada
APPLICATIONS FOR PRIVILEGES, RIGHTS AND AUTHORITY
Applications for Approval of New or Revised Depreciation Rates
Section 703.2765 - Statement A
Current through December 31, 2024
1. Statement A must consist of:
2. If the date of the study does not coincide with the date of the most recent annual report on file with the Commission, supporting schedules must be made available showing, in separate columns, the additions and reductions in book accounts made during the period between the date of the annual report and the date of the study for depreciable plant balances and accumulated provisions for depreciation. All adjustments must be clearly and fully explained in the supporting material submitted so that the plant balances and other information contained in statement A may be reconciled with the corresponding information contained in the annual report.
Added to NAC by Pub. Service Comm'n, eff. 1-6-84
NRS 703.025, 704.210