For the purposes of subsection 3 of NRS 40.6887, the Board will deem a request to have been submitted to the Board when:
1. The request has been received by the Board;
2. All the materials and documentation required by the Board pursuant to NAC 624.793 have been provided to the Board; and
3. If the Board determines pursuant to the provisions of NAC 624.794 that an investigation into the request is required, the Board has completed the investigation.
Added to NAC by Contractors' Bd. by R158-03, eff. 5-14-2004; A by R046-05, 9-7-2005
NRS 40.6887
Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.