Section 618.365 - Circumstances requiring issuance

Universal Citation: NV Admin Code 618.365

Current through February 27, 2024

The owner or lessee of a tower crane shall ensure that the tower crane has been issued a valid certificate of operation by a certifying authority:

1. Each time the tower crane is erected;

2. Each year the tower crane remains erected at one location; and

3. Each time a tower crane is repaired or modified in any way which affects the structural integrity of the crane, other than the addition or removal of sections to the mast of the crane or the addition of other components which are a permanent part of the tower crane in its working condition, such as a load block or rigging.

Added to NAC by Div. of Industrial Relations, eff. 2-25-97

NRS 618.295, 618.880

Disclaimer: These regulations may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.