Nevada Administrative Code
Chapter 535 - DAMS AND OTHER OBSTRUCTIONS
CONSTRUCTION, RECONSTRUCTION, ALTERATION AND DECOMMISSIONING OF DAMS
Section 535.320 - Emergency action plan
Current through December 12, 2024
1. To obtain an approval to impound, including a temporary approval to impound, an owner or operator of a dam classified as high hazard or significant hazard must submit to the State Engineer an emergency action plan for the dam.
2. An owner or operator of a dam classified as high hazard or significant hazard for which an approval to impound has been granted as of October 24, 2014, or that otherwise is impounding water or is capable of impounding water as of October 24, 2014, shall submit to the State Engineer an emergency action plan for the dam.
3. An emergency action plan for the dam must:
4. An owner or operator subject to this section shall:
Added to NAC by St. Engineer by R124-02, eff. 5-30-2003; A by R054-14, eff. 10/24/2014
NRS 532.120